Realizing a Waste-to-Energy Project – How to Start

Thomas Vollmeier and Nathalie Camplani

1. The need of Waste-to-Energy ...41

2. Boundary conditions ...42

3. How to start a project ...42

3.1. Stakeholders ...42

3.2. Technical approach ...43

3.3. Financing ...46

3.4. Permitting ...46

3.5. Communication / Stakeholders involvement ...46

3.6. Organization of the promoting entity ...47

4. Conclusions ...47

To realize a new Waste-to-Energy plant is a complex and long-lasting operation, with numerous obstacles which can, if not correctly approached, bring to a total failure of the project. The greatest errors are often done at the beginning. For this reason, it is very important to ensure a correct and well-planned start.

Aim of this article is to give some suggestions based on previous experiences, in order to help promoters have a higher chance of success in their initiatives.

1. The need of Waste-to-Energy

In this context we consider waste mainly as Municipal Solid Waste (MSW), hence excluding industrial, hazardous and other special waste.

The general objective in MSW-management is first of all the reduction of its produc- tion by avoiding waste producing products and reusing still valuable objects. The still produced waste is whenever technically and economically possible recycled, in order to recover materials which can be returned into production processes.

However, there is always a certain quantity of un-reusable waste which remains and must be disposed of. It is still usual in many countries, that this remaining waste is dumped in controlled (but also uncontrolled) landfills, leaving a heavy burden to the environment and to the future generations.

(3)

Policies/Str

A much more responsible way of treating the remaining waste is to convert it into inert material by an oxidation process, the most common and reliable being the combustion. Used since decades in many countries, it has in the years reached a very high technological standard, being able to guarantee an extremely performing emission control, to convert into electricity and heat a large part of the energy con- tained in the waste and to recover useful material from the resulting inert residues, i.e. metals and minerals.

Waste-to-Energy is hence an indispensable part of a modern MSW-management system.

2. Boundary conditions

Before starting with the project, it must be verified that the necessary boundary conditions are given. The main conditions are:

• The construction of a WtE-plant must be legally possible. There are many regions where such plants are explicitly banned

• The regional planning of waste management should foresee the construction of a WtE-Plant, or at least it should not explicitly exclude it

• The ownership of MSW must be legally cleared. Generally, the collected waste is owned by the local authority, which has the duty to dispose it off. But there are situations where the MSW is owned by the collector, which can be a private company. In this case the public authority has no control on the destiny of the waste.

If above conditions are not given, it is not recommendable to start a WtE-Project.

3. How to start a project 3.1. Stakeholders

One should be conscious of all the bodies and entities which are touched by such a project, in order to consider them in the implementation strategy.

Figure 1 shows the usual stakeholders involved and the interactions with the promoter.

As it appears, there are not only technical issues to be managed, but a plant must obtain the necessary authorization, the demanded financial funds must be found, and last but not least, the project must face the public opinion, which is often strongly opposed to such plants.

More details for each sector are given in the following chapters.

(4)

Policies/Str

3.2. Technical approach

Being a WtE-plant a complex industrial facility, the technical issue is one of the first to be tackled.

Basic data First of all, it is fundamental to have a clear view of the waste situation in the region where the promoter of the project is acting. Following questions must be answered:

• What is the actual total quantity of MSW produced, differentiated in type of waste (paper, glass, plastics, metals, organics, ….) and how it has evolved in the past 5 to 10 years?

• Which portion of the said types of waste is recovered for material recycling?

• What are seasonal variations in waste production and its quality?

• How is the estimated evolution of these quantities in the next 10 to 20 years, considering population growth, increase of GDP, development of separate collection of waste?

To gather the actual data is not always easy, but with some efforts generally possible. It is much more difficult to estimate the future situation and therefore various scenarios must be put down. Typically, three scenarios are developed:

project marketing funding body/financing

banks

lawyer neighbourhood

neighbourhood public opinion

NGO

NGO

authorities

lawyer

financial consultant

consulting engineer consulting

engineer

architect PR-consultant

investors public and private communities

energy purchaser

disposal of residuals

contractor

supplier of equipment

landfill

purchaser of recovered resources

technical implementation permitting

project core team

Figure 1: Main issues and interactions between stakeholders

(5)

Policies/Str

• Highest case scenario, considering the maximal evolution for all parameters

• Lowest case scenario, considering the minimal evolution for all parameters

• Middle way scenario, as an average of the above scenarios.

The following graphic shows an example of such scenarios.

Figure 2: Evolution of MSW production

180,000

150,000

120,000

90,000

60,000

30,000

2010 2015 2020 2025 2030 2035

0 waste quantity tons per year

observed data scenario a scenario b scenario c

Based on these data it is possible to evaluate the approximate quantity and quality of waste which has to be disposed of and hence to decide the capacity of the WtE plant.

Feasibility study / Siting

Once defined the waste quantity and quality which should be treated by the future facility, it is advisable to finalize a feasibility study. The main aims of such a study are:

• Determine the nominal capacity of the plant, considering seasonal variations (i.e.

touristic locations) and some reserves

• Determine the thermal power of the plant, which depends from quantity and low calorific heat of incinerated waste

• Decide number of combustion lines: one big line is less costly; two smaller lines are more flexible

• Define concept of plant:

– type of combustor: grate boiler, fluidized bed boiler – steam parameters

(6)

Policies/Str

– fluegas treatment system

– energy recovery system: only electricity, electricity and district heating/indus- trial steam

• Determine layout of plant and hence required land surface

• Find a suitable site where to build the plant, considering:

– land surface required – suitable land use regulation

– availability of infrastructure (access roads, electricity grid, water, sewage, …) – nearby presence of industrial facilities which could be interested in buying ener-

gy from the plant (steam, heat, electricity). This can improve substantially the economical result of the plant

• List all the necessary permits and authorizations and required procedures for each of them

• Draw an estimated timetable from start decision till commissioning of plant

• Estimate construction, financial and operating costs, and hence determine the re- quired gate fee.

With the results of the above study, the promoter has the basis to evaluate chances and risks of the project and to decide whether to continue or to stop it.

To invest into a feasibility study is of high interest for the promoter. Try to economize on it is not very long-sighted. In fact, such a study can have a great influence on the success of the project. As shown in Figure 3, in the very first phases of a project, good ideas as well as errors have the highest impact on the final result.

100

influenceability

feasibility study

basic engineering

permitting/tendering

detail engineering

alternativ contracts

change management

completion state 50

25

10

1/4 1/2 3/4 1

(7)

Policies/Str

Engineering

Once decided to pursue with the project, further engineering activities can be put ahead for permitting purpose and later on for procurement procedures. However, there are other issues to face first.

3.3. Financing

Private promoters must create a financing structure comprising proprietary capital, external capital through for instance capital stock or equity funds, as well as bank loans and insurance policies. Often promoters request the contractors who supply and build the plant, to participate with capital stock.

Often the building up of a financing structure is very time and money consuming, since all the involved parties want to have enough guaranties that the project has a positive issue, hence asking for technical and non-technical due diligences. Adequate time must be considered for this task.

In case of public promoters, the required credits must first be approved by the deciding entity (legislative body) and sometimes even through a public referendum. After this approval, usually bank loans are searched, which in this case are less difficult since the public authority offers enough guarantees being usually always solvent.

3.4. Permitting

To obtain all necessary permits and authorizations is often a long-lasting procedure, on one side because of the complexity of the object to be authorized, but moreover because objections and administrative appeals against a WtE-Plant are practically unavoidable.

Therefore, the timetable of permitting is very uncertain.

In order to possibly reduce this uncertainty, it is advisable to:

• Meet the authorizing authorities in advance and clear with them the correct proce- dures to be followed and the required documents and studies to be supplied. This can minimize losses of time. Furthermore, the personal contact with the officers in charge of the authorization request can facilitate the whole procedure

• Include the public (neighborhood, NGOs, other interested entities) in the proce- dure (see following chapter).

3.5. Communication / Stakeholders involvement

WtE-Plants are notoriously not very favored objects, often ideologically demonized.

Furthermore, they can be in conflict with other actors of the waste management system or influence the political arena. Typical opponents to such projects are:

• Neighbors of the future plant: the nimby (not in my backyard) syndrome is every- where present

• NGOs and environmental activists: WtEs are favored opposition objects, since they

(8)

Policies/Str

• Owners of landfills: the waste which goes to a WtE-Plant doesn’t bring them any revenue

• Politicians: favoring this type of infrastructure does not usually increase the number of votes at the next elections.

Therefore, it is advisable to promote a good and professional communication since the beginning of the project, involve and understand the worries and concerns of the opponents and try to accommodate them as far as possible.

Investment in these activities is well placed money.

3.6. Organization of the promoting entity

To face all the issues described in the precedent chapters requires a solid and profes- sional organization of the promoter.

At least following competences should be foreseen:

• Consulting engineer: to produce the feasibility studies, to provide all the enginee- ring services to prepare technical documents for permitting and procurement

• Legal advisor: to prepare contracts, solve legal issues, organize complaint management

• Financial advisor: helping set up of financing structure

• PR-consultant: to organize communication and involvement of stakeholders.

Very important is the project management, which can be internal of the promoter or external. The project manager must be an experienced person, knowing what it means to realize a WtE-Plant. He must guarantee a constant overview of the project and the coordination of all the subjects directly involved in the project team.

4. Conclusions

The realization of a Waste-to-Energy plant is a complex task. Bring it successfully to the end is not obvious. The first phases of such a project are crucial and enough time and money should be allocated to them in order to guarantee a well-organized and thoroughly planned start.

Contact Person

Thomas Vollmeier TBF + Partner AG Planer und Ingenieure Via Besso 42

6900 Lugano SWITZERLAND +41 9161026-21

(9)

Bibliografische Information der Deutschen Nationalbibliothek Die Deutsche Nationalbibliothek verzeichnet diese Publikation in der Deutschen Nationalbibliografie; detaillierte bibliografische Daten sind im Internet über http://dnb.dnb.de abrufbar

Thiel, S.; Thomé-Kozmiensky, E.; Winter, F.; Juchelková, D. (Eds.):

Waste Management, Volume 9 – Waste-to-Energy –

ISBN 978-3-944310-48-0 Thomé-Kozmiensky Verlag GmbH

Copyright: Elisabeth Thomé-Kozmiensky, M.Sc., Dr.-Ing. Stephanie Thiel All rights reserved

Publisher: Thomé-Kozmiensky Verlag GmbH • Neuruppin 2019 Editorial office: Dr.-Ing. Stephanie Thiel, Elisabeth Thomé-Kozmiensky, M.Sc.

Layout: Claudia Naumann-Deppe, Janin Burbott-Seidel, Sarah Pietsch, Ginette Teske, Roland Richter, Cordula Müller, Gabi Spiegel Printing: Universal Medien GmbH, Munich

This work is protected by copyright. The rights founded by this, particularly those of translation, reprinting, lecturing, extraction of illustrations and tables, broadcasting, micro- filming or reproduction by other means and storing in a retrieval system, remain reserved, even for exploitation only of excerpts. Reproduction of this work or of part of this work, also in individual cases, is only permissible within the limits of the legal provisions of the copyright law of the Federal Republic of Germany from 9 September 1965 in the currently valid revision. There is a fundamental duty to pay for this. Infringements are subject to the penal provisions of the copyright law.

The repeating of commonly used names, trade names, goods descriptions etc. in this work does not permit, even without specific mention, the assumption that such names are to be considered free under the terms of the law concerning goods descriptions and trade mark protection and can thus be used by anyone.

Should reference be made in this work, directly or indirectly, to laws, regulations or guide- lines, e.g. DIN, VDI, VDE, VGB, or these are quoted from, then the publisher cannot ac- cept any guarantee for correctness, completeness or currency. It is recommended to refer to the complete regulations or guidelines in their currently valid versions if required for ones own work.

Abbildung

Figure 1:   Main issues and interactions between stakeholders
Figure 2:   Evolution of MSW production

Referenzen

ÄHNLICHE DOKUMENTE

The aim was to find a site for the new plant in the area covered by the Tampere district heating network because district heating load is large enough to fully utilize the heat

In this methodology, it is of paramount importance to not only take into account direct emissions, which are defined as emissions that originate from waste management acti- vities

In order to explore the whole potential of sustainable waste management, it would be important that EU waste legislation will, after setting targets for landfill diversion and

From the review of the EU waste legislation, through the Eu- ropean Commission’s Communication on Waste-to-Energy, to the work on the review of Waste Treatment and Waste

In the search for long-term solutions to the existing problem, and the implementation of Waste to Energy in Greece, the six different WtE technico-economical models give an

Waste-to-Energy is also a cornerstone between the Circular Economy and the Energy Union strategy, as it provides an opportunity for a better use of residual waste while

Im Ergebnis wird erarbeitet, ob es sich im vorliegenden Fall um eine Abfallbehandlungsanlage handelt, die sich größtenteils durch eine Annahmegebühr des angelieferten

Even if waste incineration plants are politically desired in Poland – the national waste management plan 2014 defines the thermal recycling of waste as the preferred treatment