• Keine Ergebnisse gefunden

MANAGEMENT OF THE BEDLOAD TRANSPORT OF THE MILIBACH TORRENT FOR FLOOD PROTECTION PURPOSE

N/A
N/A
Protected

Academic year: 2022

Aktie "MANAGEMENT OF THE BEDLOAD TRANSPORT OF THE MILIBACH TORRENT FOR FLOOD PROTECTION PURPOSE"

Copied!
2
0
0

Wird geladen.... (Jetzt Volltext ansehen)

Volltext

(1)

MANAGEMENT OF THE BEDLOAD TRANSPORT OF THE MILIBACH TORRENT FOR FLOOD PROTECTION PURPOSE

PHYSICAL MODEL BASED STUDY

Fadi Hachem1, Beatrice Herzog2, Jean-Louis Boillat3 and Anton Schleiss4

INTRODUCTION

The Milibach River between Hasliberg-Reuti and Meiringen agglomerations in Switzerland has a limited hydraulic capacity leading to frequent flooding. During the 2005 flood event, large populated areas were inundated and damages exceeding many millions of Swiss francs occurred (Fig. 1). The deficit of the river flow capacity is essentially caused by a reduction of river cross sections due to local sediment deposits which lead to the overtopping of the lateral embankments.

RISK MANAGEMENT

Aiming to manage the flood risk, a protection concept in the Reuti region has been proposed by Herzog Ingenieure. It consists in adjusting the layout, the cross-section and the longitudinal profile of the river and fitting out the neighboring lands inside an area of about 40 hectares. The main purpose is to create sediment deposition terraces, able to laminate, up to 75%, the bed load transport towards the downstream part of the river. Therefore, the flood peak can cross Meiringen without excessive sediment deposition, keeping the hydraulic capacity high enough to transit 100 years return period floods.

Considering its high sensitivity level, the optimization of the project was done by physical modeling.

The experimental tests were carried out on a physical set-up built in the Laboratory of Hydraulic Constructions at scale 1/30, according to Froude similarity. A plan view of the project with the physical model borders are shown on Fig. 2.

Fig. 1 Project location and flooded zones during the 2005 event.

Fig. 2 Topographic plan view and borders of the physical 1/30 scaled model.

PHYSICAL MODEL AND TEST RESULTS

The physical scaled model tests revealed to be a powerful tool to optimize the project and to analyze the efficiency of the proposed solution. Several tests have been carried out on different configurations built by adding weirs across the river bed, by changing locally the layout and/or the longitudinal slope

1 Ph.D. candidate. Ecole Polytechnique Fédérale de Lausanne, Laboratory of Hydraulic Constructions, Switzerland

2 Director of Herzog Ingenieure AG, Dorfstr. 10, 3073 Gümligen, Switzerland (e-mail: herzog@herzog-ingenieure.ch)

3 Dr. Eng. Chemin de la Brotte 4, 1163 Etoy, Switzerland (e-mail: jean-louis.boillat@epfl.ch)

4 Prof. Director of the Laboratory of Hydraulic Constructions. Ecole Polytechnique Fédérale de Lausanne, Switzerland 12th Congress INTERPRAEVENT 2012

Grenoble / France – Extended Abstracts www.interpraevent.at

Flooded areas River obstruction zones Project

boundaries

Borders of the physical model

4.2 m

11.0 m Actual river layout

Deposition terraces New river

layout

2 1 3

4

New bridge

- 154 -

(2)

of the river and by smoothing the transversal slopes of the deposition terraces. Two hydro- and solidographs with a return period of 100 years and with two different durations have been used for optimization puposes. They are characterized by prototype peak water flows of 7 and 15 m3/s and solid flows of 1.0 and 1.5 m3/s, respectively. An extreme flood with a peak water flow of 25 m3/s (peak solid flow of 2.7 m3/s) was also tested to evaluate the robustness of the optimized solution. A picture of the final configuration is given in Fig. 3.a. The sediment depositions at the end of the two 100 years floods and the extreme event are shown on Figs.3.b, c and d, respectively.

(a) (b) (c) (d)

Fig. 3 a) Optimized configuration of the project, b) sediment deposition at the end of the 100 years flood (peak flow of 15m3/s), c) sediment deposition at the end of the 100 years flood (peak flow of 7m3/s), and d) sediment deposition at the end of the extreme flood event (peak flow of 25m3/s)

The physical tests have led to the following adjustments of the initial configuration proposed by Herzog Ingenieure: (i) reduction of the longitudinal river slope near terraces 3 and 4, (ii) implantation of four weirs across the main river bed, (iii) reduction of the transversal slope of terrace 3 from 5 to 1%, and (iv) construction of three small rock dams of 1.5 m height to close the three terraces and lead the flow towards the main river.

IN-SITU WORKS

The execution of the project has started during summer 2010. Fig. 3.a shows the construction site downstream from the new bridge including terraces 2 and 3 and two weirs inside the river bed. The new bridge and the upper river bed section are shown in Fig. 3.b. As the flood events are expected to occur only every 20 years, the area remains in private property and agricultural use.

(a) (b)

Fig. 4 Pictures of the construction site, a) from the bridge towards downstream, b) towards upstream Keywords: flood risk management, sediment transport, sediment retention, river training works.

1

Deposition terraces 2

3

4

- 155 -

Referenzen

ÄHNLICHE DOKUMENTE

Approaches using relational database systems (DBSs) were already proposed to facilitate data integration and enable declarative access to genome data for analysis applications [15,

This idea was confirmed by comparing the peak discharges of the 2000 and 2001 events to the peak discharges proposed by the hazard assessment: the major torrent, the Grand

After the first agreement was concluded in 2006 in accordance with Article 15a of the B-VG (Federal Constitutional Act) between the Federal Government and provinces of

The physical tests led to the following main adjustments of the initial configuration: (i) increase of the height of the upstream part of the lateral dyke, (ii) decrease of the

It can be summarized that the participants of the stakeholder workshop think that one of the best measures to raise public awareness is to do education on natural hazards in school,

The purpose here is also to put in light the important role of mountains in the preventive flood risk management and to explore a paradox: despite the fact that these mountains

Therefore, taking benefit of recent advances in their availability, the analysis presented here relies on a micro-scale procedure (Ernst et al. 2010), which involves hazard modelling

A new model for flood prediction and management of the Rhone river basin is presented. This 5500 km 2 mountainous catchment area contains 10 major hydropower plants with