• Keine Ergebnisse gefunden

1. Reactor Coolant Pressure Boundary PWR

Design Characteristics Construction

Line 1 Construction

Line 2 Construction

Line 3 Construction Line 4

Number of Loops 2 or 4 3 or 4 4 4

Suitability of the components for non-destructive testing

Yes, with minor restrictions Yes

Components - Seamless forged rings for

vessels

Reactor pressure vessel, steam generators (primary side only)

Reactor pressure vessel, steam generators,

pressuriser - Seamless pipes Main coolant line

with minor restrictions

Main coolant line

Materials - Ageing-resistant ferritic

fine-grained structural steels with stabilised austenitic cladding

All components and pipes with nominal diameter > 400 mm

Like construction lines 1-3, but with optimised

qualities - Ageing-resistant stabilised

austenitic steels

All pipes with nominal diameter < 400 mm and component internals

- Corrosion-resistant steam generator tube material (Incoloy 800)

Yes (after exchange

of steam generators in

one plant)

Yes

Application of the rupture preclusion concept

Post-commissioning qualification Prior to commissioning

From the start of planning Reduction of embrittlement from

neutron radiation exposure

Use of dummy fuel elements

and special fuel element management

Optimised welding material and enlargement of water gap in the reactor pressure vessel to

reduce neutron fluence

1. Reactor Coolant Pressure Boundary BWR

Design Characteristics Construction Line 69 Construction Line 72 Re-circulation pumps integrated

in the reactor pressure vessel

8 to 10 8

Suitability of the components for non-destructive testing

Yes,

with minor restrictions

Yes

Components - Seamless forged rings for

reactor pressure vessels

No Yes, except: closure head, bottom

head

- Seamless pipes Yes,

after replacement of pipes

Yes

Materials - Ageing-resistant ferritic

fine-grained structural steels

Reactor pressure vessel, main-steam and feedwater pipes - Ageing-resistant stabilised

austenitic steels

Pipes *), partly backfitted by replacements, in addition reactor pressure vessel internals and cladding Application of the break

preclusion concept

Post-qualification partly through pipe replacement

Prior to planning;

under review **) Reduction of embrittlement from

neutron radiation exposure

Special fuel element management (low leakage loading)

*) for KRB II: only stabilised austenitic pipes are used

**) for KRB II: the break preclusion concept was approved by the competent authority with a modification licence

2. Emergency Core Cooling PWR

Design Characteristics Construction

Line 1 Construction

Line 2 Construction

Line 3 Construction Line 4 Number of emergency core

cooling trains/capacity

4 trains of at least 50 % each

Pump head of high-pressure pumps

Approximately 110 bar

Secondary circuit shutdown in case of small leaks

Manually or fully automatic

Automatic partial shutdown

or fully automatic

fully automatic

Number of borated water flooding tanks

3 or 5 4,

in some cases twin tanks or 4 flooding pools Pump head of

low-pressure injection pumps

1 plant 8 bar 1 plant18 bar

Approximately 10 bar

Accumulators (injection pressure)

1 per loop (26 bar);

1 plant without accumulators

1 or 2 per loop (25 bar)

2 per loop (25 bar)

Sump pipe before outer penetration isolation valve

Single pipe (1 plant without

sump suction pipe)

Guard pipe construction,

some with leakage monitoring

Guard pipe construction with leakage monitoring

Place of installation of the active emergency core cooling systems

Separate building, reactor building

or annulus

Annulus

2. Emergency Core Cooling BWR

Design Characteristics Construction Line 69 Construction Line 72 Number of trains of the

high-pressure

safety injection system (capacity)

1 train

(steam turbine, up to 50 bar main steam pressure,

approx. 300 kg/s)

3 trains

(electric pumps, 3 x 70 kg/s)

Diversified

high-pressure safety injection system

1 train (electric pump approx. 40 kg/s)

No

Pressure relief 7 to 11 safety and pressure relief valves,

additionally 3 to 6 motorised pressure relief valves

11 safety and pressure relief valves,

additionally 3 motorised pressure relief valves

Intermediate-pressure injection system

No 1 train

(additional independent RHR system; electric pump, 40 bar) Number of low-pressure

emergency core cooling trains/capacity

4 trains of 50 % each 3 trains of 100 % each

Low-pressure safety system with diversified injection

1 x 100 % core flooding system

No

Backfeed from containment sump

Yes, via active systems

Yes,

via passive systems with 4 overflow pipes Place of installation of the

emergency core cooling systems

In separate rooms of the reactor building

In separate rooms of the reactor building, intermediate-pressure system

in a bunkered building

3. Containment Vessel PWR

Design Characteristics Construction

Line 1 Construction

Line 2 Construction

Line 3 Construction Line 4 Type Spherical steel vessel with surrounding concrete enclosure, annular gap and constant internal subatmospheric pressure Design pressure

(overpressure)

1 plant 2.99 bar 1 plant 3.78 bar

4.71 bar 5.3 bar 5.3 bar

Design temperature 1 plant 125°C 1 plant 135°C

135°C 145°C 145°C

Material of steel vessel (main structure)

BH36KA;

HSB50S

FB70WS;

FG47WS;

BHW33

FG51WS;

15 MnNi 63;

Aldur 50/65D

15 MnNi 63

Wall thickness of steel vessel in the spherical region remote from discontinuities

Up to 25 mm Up to 29 mm Up to 38 mm 38 mm

Airlocks - Equipment airlock Single or

double seals without evacuation

Double seals with evacuation

- Personnel airlock Single or double seals

without evacuation

Double seals with evacuation

- Emergency airlock One with single seal

One with double

seals and evacuation

Two

with double seals and evacuation

Penetrations

- Main steam line One isolation valve outside of containment

- Feedwater line One isolation valve each inside and outside of containment - Emergency core cooling

and auxiliary systems

With a few exceptions, one isolation valve each inside and outside of containment

One isolation valve each

inside and outside of containment - Ventilation systems One isolation valve each inside and outside of containment

3. Containment Vessel BWR

Design Characteristics Construction Line 69 Construction Line 72

Type Spherical steel vessel

with pressure suppression pool located in the thorus

Cylindrical pre-stressed concrete shell with annular pressure suppression pool Design pressure

(overpressure)

Up to 3.5 bar 3.3 bar

Design temperature Approximately 150°C

Material of steel vessel (main structure)

WB25; Aldur50D, BHW25 TTSTE29

Wall thickness of steel vessel outside the concrete support

Depending on geometry and design:

18 mm to 50 mm, 18 mm to 65 mm, 20 mm to 70 mm, 25 mm to 70 mm

8 mm steel liner

Number of pipes in the pressure suppression pool

Depending on the plant:

58, 62, 76 or 90

63

Immersion depth of pipes in the pressure suppression pool

2.0 or 2.8 m 4.0 m

Inertisation of the air in the pressure suppression pool

Yes Yes

Inertisation of the drywell Yes No

Airlocks In all cases double seals with evacuation

- Equipment airlock None

- Personnel airlock Leading to control rod drive chamber, for personnel and for equipment transports

- Emergency airlock One from control rod drive chamber One from control rod drive chamber and one above pressure suppression pool

Penetrations - Main steam line/

Feedwater line

One isolation valve each inside and outside of containment

- Emergency core cooling and auxiliary systems

Emergency core cooling system in the area of the pressure suppression pool and several small pipes with two isolation valves

outside of containment, otherwise one isolation valve each inside and outside of containment - Ventilation system Two isolation valves outside of containment

4. Limitations and Safety Actuation Systems PWR

4.1 Limitations

Design Characteristics Construction

Line 1 Construction

Line 2 Construction

Line 3 Construction Line 4 Reactor power limitation 1 plant yes,

1 plant no

Yes

Control rod movement limitation

Yes

(monitoring of shut-down reactivity ) Limitations of coolant

pressure, coolant mass and temperature gradient

Coolant pressure

Partially Yes

4.2 Safety Actuation Systems

Design Characteristics Construction

Line 1 Construction

Line 2 Construction

Line 3 Construction Line 4 Actuation criteria derived

from accident analysis

Largely, yes Yes

Different physical actuation criteria for reactor protection system

Yes, or higher-grade

redundancy

Yes, or

diverse actuation channels

Failure combinations Random failure, systematic failure,

consequential failures, non-availability due to maintenance Testing of reactor protection

system is possible during power operation

Yes, largely by automatic self-monitoring (of functional readiness)

Actuation of protection systems

Apart from a few exceptions, all actions are performed automatically, and manual actions are not required within the first 30 min

after the onset of an accident.

4. Limitations and Safety Actuation Systems BWR

4.1 Limitations

Design Characteristics Construction Line 69 Construction Line 72

Fixed reactor power limitation Yes,

speed reduction of forced-circulation pumps Variable reactor power limitation Yes,

control rod withdrawal interlock start-up interlock of forced-circulation pumps

Local power limitation Yes,

control rod withdrawal interlock

Yes,

control rod withdrawal interlock and speed reduction of forced-circulation pumps

4.2 Safety Actuation Systems

Design Characteristics Construction Line 69 Construction Line 72 Actuation criteria derived

from accident analysis

Largely, yes Yes

Different physical actuation criteria for reactor protection system

Yes, or

higher level of redundancy

Yes, or

diversified actuation channels

Failure combinations Random failure, systematic failure,

consequential failures, non-availability due to maintenance Testing of reactor protection

system is possible during power operation

Yes, largely by automatic self-monitoring (of functional readiness)

Actuation of protection systems Apart from a few exceptions, all actions are performed automatically, and manual actions are not required within the first

30 min

after the onset of an accident.

5. Electric Power Supply PWR

Design Characteristics Construction

Line 1 Construction

Line 2 Construction

Line 3 Construction Line 4 Number of independent

off-site power supplies

At least 3

Generator circuit breaker Yes

Auxiliary station supply in the case of off-site power loss

Yes, load rejection to auxiliary station supply

Emergency power supply 2 trains with 3 diesels altogether, or

4 trains with 1 diesel each

4 trains with 1 diesel each

Additional emergency power supply for the control of external impacts

2 trains 1 - 2 trains, unit support system at

one double-unit plant

4 trains with 1 diesel each

Uninterruptible DC power supply

2 x 2 trains 4 trains (except for 1 plant with 2 x 4 trains)

3 x 4 trains

Protected DC power supply 2 hours

Separation of trains Intermeshed emergency power supply,

physical separation of the

emergency power supply

grids

Partially intermeshed emergency power

supply, physical separation of the emergency power

supply grids

Largely non-intermeshed emergency power supply, physical separation of the emergency power supply grids

5. Electric Power Supply BWR

Design Characteristics Construction Line 69 Construction Line 72 Number of independent

off-site power supplies

At least 3

Generator circuit breaker Yes

Auxiliary station supply in the case of off-site power loss

Yes, load rejection to auxiliary station supply

Emergency power supply 3 or 4 trains with 1 diesel each

5 trains with 1 diesel each Additional emergency power

supply for the control of external impacts

2 or 3 trains with 1 diesel each

1 - 3 trains with 1 diesel each

Uninterruptible DC power supply 2 x 2 trains 2 x 3 trains

Protected DC power supply 2 hours

Separation of trains Partially intermeshed emergency power supply,

physical separation of the emergency power supply grids

Largely non-intermeshed emergency power supply, physical separation of the emergency power supply grids

6. Protection against External Impacts PWR

Design Characteristics Construction

Line 1 Construction

Line 2 Construction

Line 3 Construction Line 4 Earthquake Design of components important to safety

in accordance with site-specific load assumptions Aircraft crash and pressure

waves from explosions

Not considered in the design,

later risk assessment,

separate emergency

systems

Different designs, separate emergency

systems

Design in accordance with the nuclear safety regulations

(→ Article 17 (i)),

emergency systems integrated in the safety system

6. Protection against External Impacts BWR

Design Characteristics Construction Line 69 Construction Line 72 Earthquake Design of components important to safety

in accordance with site-specific load assumptions Aircraft crash and pressure

waves from explosions

Different designs, up to status of construction line 72, emergency systems separate, or

integrated in the safety system

Design in accordance with the nuclear safety regulations

(→ Article 17 (i)), emergency systems integrated in the safety system