• Keine Ergebnisse gefunden

RELIABILITY OF AVALANCHE PROTECTION STRUCTURES Olivier Marco

N/A
N/A
Protected

Academic year: 2022

Aktie "RELIABILITY OF AVALANCHE PROTECTION STRUCTURES Olivier Marco"

Copied!
2
0
0

Wird geladen.... (Jetzt Volltext ansehen)

Volltext

(1)

12th Congress INTERPRAEVENT 2012 Grenoble / France – Extended Abstracts www.interpraevent.at

RELIABILITY OF AVALANCHE PROTECTION STRUCTURES

Olivier Marco1

INTRODUCTION

This article is a contribution to the ongoing debate in France regarding the granting of building permits below natural hazard protection structures.

The first step is to determine the reliability of the structure.

This reliability is based on the following 3 principles:

1. The structure has a clearly identified owner, responsible for its maintenance.

2. The technical characteristics of the structure actually correspond to the phenomenon for which it was designed

3. Any increase in the hazard resulting from a malfunction of the device has been evaluated.

This article concerns the possibility of an Avalanche Active Protection Structure (AAPS2), such as metallic nets, horizontal and vertical-framed metallic barriers (excluding earthworks (terracing) and reforestation) actually increasing the hazard. It is drawn from a survey among all the RTM departments (officials departments in charge of the Restoration of Mountain Territories in the French Alps and Pyrenees).

INCREASED HAZARD RESULTING FROM FAILURE OF A PROTECTION STRUCTURE The notion of an increased hazard following failure of a structure is very common in risk analysis and more particularly in the field of hydraulics. Failure of a dam can lead to an exceptional hazard which would not have happened if this structure were not present. Such events have been observed in the past and sometimes caused major disasters in France (failure of Malpasset dam). The corresponding phenomena are today beginning to be understood scientifically and can be described both qualitatively and quantitatively.

Can this notion be transposed to AAPS2 ?

This notion was introduced for the first time into a provisional version of the avalanche hazard prevention plan (PPR) methodology guide, available from the www.prim.net website. It recommends

"assessing the absence of aggravating effects due to a threshold effect with regard to nets and fences which would, in certain exceptional conditions, be covered with snow [Fig. 1] potentially leading to avalanches that are more voluminous than if purely natural".

Up to now no scientific approach has been proposed. In the absence of any scientific certainty able to quantify the increased risk resulting from the failure of an active avalanche protection structure, field observation could be of particular value in attempting to identify some initial answers.

HAVE SUCH MALFUNCTIONS ALREADY BEEN OBSERVED?

1. Methodology

A limited survey through the existing structures and the problems these have encountered was made by the RTM Departments throughout the whole of the French Alps and Pyrenees. Although this inventory, based on archives and only a few field visits, cannot claim to be exhaustive, there is no doubt that, in line with their mission of assessing the official authorities since 1860, the RTM

1 Dr. Olivier Marco. National Delegation for Natural Hazards and RTM at the Office National des Forêts /RTM France technical department

2 AAPS: English translation for Dispositif de Protection Paravalanche Actif (DPPA)

- 256 -

(2)

departments nonetheless have stored data, however scant sometimes, on most events having had significant consequences for the protected assets after the failure of an AAPS.

Fig. 1 Structure destroyed by an avalanche 2. Main findings

This survey highlights malfunctions which are most often linked to mistakes in the design and installation of the structures, as well as to a lack of upkeep. However, in a vast majority of cases, the avalanche which destroyed the structure did not exceed its known expansion limits.

However, in only one very particular case, it would seem probable that the failure of the structure enabled a far larger avalanche to develope than would have occurred on the site if it had not been equipped in that way. This case is described as follows:

It consists of an anti-avalanche net system devised for the protection of a ski slope against frequent avalanches coming from smooth and very steep (up to 45°) rock slabs. Those slabs do not naturally allow a great accumulation of snow. After the upper line of the system broke under overload, the entire snow cover, artificially held, set in motion, taking along with it the whole of the system.

Fortunately, no injury nor human loss were reported.

CONCLUSION

The two main conclusions are:

 To the best of our knowledge, no disasters have occurred in France as a result of an AAPS malfunction. Therefore, those systems have allowed an important mitigation of the avalanche danger over human-occupied areas. In fact, in certain European countries, these structures are taken into account when drawing up risk maps.

 The study however shows that an aggravation of the hazard as a result of an AAPS malfunction cannot be completely ruled out in particular situations, such as installations on steep smooth slabs. A detailed study is thus necessary when sites such as these have to be equipped in order to protect inhabited areas.

Keywords: avalanche, avalanche protection structures, natural hazard protection

- 257 -

Referenzen

ÄHNLICHE DOKUMENTE

Analysis and Evaluation of Rockfall Hazard Page 37 Figure 59: Profile III - Present Situation - Total Kinetic Energy on Barrier ... XLVIII Figure 60: Profile IV - Present Situation

Airbag not released in emergency. Airbag not released in emergency. 2) Hazards are created during design. 3) Hazards are comprised of three components. 4) Hazards and mishap risk

The parameters were sampled in ranges adapted to the reference barrier capacity (Table 1). A free-board was considered to avoid direct impact of blocks on the top

This paper shows how DAMs can help DMs assess the effectiveness of a protection system, such as a cluster of check dams. Several analysis steps are proposed: 1) specification of the

In order to visualize the benefits resulting from technical mitigation, a toolbox was developed within an open-source GIS application that allows for an assessment of gains

Up to now the dangers emerging from groundwater have been neglected completed, primarily because groundwater processes are not considered as natural hazards in Swiss

Based on the results of the previous 4 steps different scenarios had been analyzed. The most likely scenario acts on the assumption of the failure respectively

Project Title: Assessing the risk of a large hydropower dam failure Hosting Institution: Paul Scherrer Institut, Villigen, Switzerland.. Abstract: Dam break analysis is an