• Keine Ergebnisse gefunden

The Maschänserrüfe project: structural measures against debris flow hazard

N/A
N/A
Protected

Academic year: 2022

Aktie "The Maschänserrüfe project: structural measures against debris flow hazard"

Copied!
2
0
0

Wird geladen.... (Jetzt Volltext ansehen)

Volltext

(1)

318 | INTERPRAEVENT 2016 – Extended Abstracts IP_2016_EA020

INTRODUCTION

Since the retreat of the Rhine Glacier after the last ice Age (about 10‘000 years b.p.), the debris flows from the Maschänserrüfe and the Scalärarüfe formed an impressive alluvial fan in the Rhine Valley. Due to the specific topographic and geologi- cal situation, debris flows occur regularly every year. While the average annual debris yield is around 25‘000 m3, the volume of single events may vary between 1‘000 and 150‘000 m3.

In order to protect the nearby village Trimmis and the agricultural land on the fan, longitudinal dams and drop structures had been built to stabilize the torrent beds and to prevent debris flow break-outs in the 19th century. In 1964, a large sediment retention basin with a capacity of 400‘000 m3 was built at the confluence of the two main channels Maschänserrüfe and Scalärarüfe. A dosage channel system - developed and optimized based on physi- cal and numerical simulations - was added in the basin in 2002, in order not only to limit debris flow volume but also limit the outflow discharge

(Schatzmann et al., 2007). The main goal was to protect the International Highway and both the National Railway SBB and the Private Railway RhB which cross the Maschänserrüfe approximately 2 km downstream of the retention basin.

PROJECT

Due to rehabilitation of the International Highway the debris flow channel in that section is recon- structed likewise. The project perimeter comprises the last 360 m of the Maschänserrüfe. In the area of the bridge crossings, the current river flows in a prismatic, fixed channel. Between the two cross- ings, the Maschänserrüfe has a mobile bed that is stabilized by concrete sills. Aside from one section where the riverbank is protected by a riprap, the riverbanks consist of concrete sidewalls. Due to the high abrasive damage of the passing debris flows, the structures have to be replaced and the bed and

sidewalls must be stabilized. Furthermore, to obtain the required discharge capacity below the new highway, the channel bed has to be lower by 1 m.

In addition to the above mentioned transportation lines, another three pipelines cross the Maschänser- rüfe in the project perimeter: (1) a long-distance heat line; (2) a high pressure gas pipeline; and (3) a wastewater disposal line.

STRUCTURAL MEASURES

The replacement of the bank protection requires the underpinning of the existing sidewalls and abutments over a length of 600 m. In some sec- tions, the extent of the underpinning amounts to 3-4 m, which equals the original wall size. To provide stability against gliding, the underpinning is equipped with a concrete bracing grounded deep under the riverbed (Fig.1 and 2). In addition every 15 m along the channel, ferroconcrete fingers sized 0.6 m x 1.0 m connect the bracing with the other sidewall to further enhance sidewall stability.

The lowered bed is stabilized with 17 block stone weirs constructed in regular intervals. The bed below the bridges is fixed with an artificial armour layer of blocks laid in concrete. Individual sills that prevent erosion and act as a river consolidation secure the pipeline crossings.

One of the main challenges during construction is to provide a high quality block structure. In order to convey the debris flow, it is essential that the channel surface, i.e. the bed and the banks exhibit a smooth surface. To achieve this goal, the insertion of the blocks in the bed and the banks has to occur with caution and skill. Given the blocks weights of up to 5 tons, it is crucial that the master builder and the site manager are experienced and that the project provides appropriate time and budget.

EMERGENCY ACTION PLAN

In order to minimize the risks during construction an emergency action plan was set into operation.

The Maschänserrüfe project: structural measures against debris flow hazard

Markus Schatzmann, Ph.D1; Marius Junker, MSc2

HAZARD AND RISK MITIGATION (STRUCTURAL, NONSTRUCTURAL MEASURES, INSURANCE)

(2)

INTERPRAEVENT 2016 – Extended Abstracts | 319

This plan consists of three elements: (1) Prevention by adapting the construction process to the weather forecast; (2) Alarm, i.e. stop the construction works when the precipitation forecast exceeds a prede- fined critical value; and (3) Emergency, i.e. evacua- tion of the construction site when the sensor system in the upper catchment basin detects an actual debris flow. The alarm system applies to the channel construction in the winter half year and to the highway construction in the summer half year.

The alarm system can prevent considerable damage to persons on the construction site if adequately installed. An adequate use implies the establish- ment of risk awareness on the side of the contrac- tor. The supervision of the implementation by a hydraulic engineering expert is vital for the success.

One main task of this expert is to assess the risk situation and to support the contractor on the construction site.

REFERENCES

Schatzmann M., Tognacca C., Bezzola

G.R., Bischoff, A. (2007). The Maschänserrüfe project - A system of debris flow discharge and volume control? Proc. of the 4th Intern. Conf.

on Debris Flow Hazards Mitigation: Mechanics, Prediction, and Assessment, Sept 10-13, Chengdu, China, Edited by Chen&Mayor, p. 669-679.

Figure 1. Armouring of the underpinning of the sidewall with bracing at the foot Figure 2. Formwork of the underpinning of the sidewall ready to be filled with concrete

KEYWORDS

Debris flow discharge control; Structural measures; Viscous debris flows; Emergency action plan

1 Basler&Hofmann Consulting Engineers, Zurich, SWITZERLAND, markus.schatzmann@baslerhofmann.ch 2 Rural Engineer ETH Zurich, Flood protection, debris flows

Referenzen

ÄHNLICHE DOKUMENTE

Both the proposed and SWCB methods had similar decreasing trend of effective rainfall, and were applicable in the debris flow monitoring and warning. More cases

In a collaboration between the Mountain Basins Service of the Autonomous Province of Trento (Servizio Bacini Montani) and the University of Trento, Faculty of Engineering,

Several empirical relations for debris flow (Rickenmann, 1999, D’Agostino et al., 2010) and two commercial two-dimensional models (FLO-2D and RAMMS) have been used to assess

Most conventional facilities for woody debris trapping are installed on the cross-section surface of a sabo dam, where the water flows past, and in accordance with the “Manual of

Considering that the flow also transported at least some bedload, and sediment deposition at the upstream reach took place within a shorter period of time than the total duration

The topographic indices for sediment transport capacity index, hypsometric integral, elevation-relief ratio, stream power index, form factor, topographic wetness index,

(Point A, B, C are the specified-output points in the upstream, midstream and downstream respectively, especially point C is the front of final deposition from the

Im Frühjahr 2000 traten großflächige Waldbrände an der Ostküste der Republik Korea auf. Durch den Niederschlagseintrag wurden zahlreiche flächenhafte Rutschungen ausgelöst, die