• Keine Ergebnisse gefunden

LANDSLIDE DAM HYDROLOGICAL OBSERVATION AND HYDROLOGICAL BALANCE CALCULATION PROCEDURES

N/A
N/A
Protected

Academic year: 2022

Aktie "LANDSLIDE DAM HYDROLOGICAL OBSERVATION AND HYDROLOGICAL BALANCE CALCULATION PROCEDURES"

Copied!
2
0
0

Wird geladen.... (Jetzt Volltext ansehen)

Volltext

(1)

Flow rate of leakage Flow rate of

drainage pump

Change in flooding Dischage of

diversion channel

Rainfall Inflow of landslide dam Overflow channel

Landslide dam

Groundwater recharge

LANDSLIDE DAM HYDROLOGICAL OBSERVATION AND HYDROLOGICAL BALANCE CALCULATION PROCEDURES

Soichi KAIHARA

1*

, Noriko TADAKUMA

1

, Yasumasa FUJIWARA

1

,Wataru SAKURAI

2

, Makoto OYAMA

3

and Ryo SAKAI

2

1Eight-Japan Engineering Consultants Inc., Japan

2 Kii Mountain District Sabo Office, Kinki Regional Bureau, Ministry of Land,Inflastructure,Transport and Tourism, Japan

3Kinki Regional Bureau, River Division, Ministry of Land,Inflastructure,Transport and Tourism, Japan

*Corresponding author. E-mail:kaihara-so@ej-hds.co.jp

INTRODUCTION

Numerous landslide dams formed in southern Nara Prefecture following the over 1,000 mm of rainfall caused by typhoon no. 12 in 2011, and some of these remain. When the water level rises, these dams pose a risk of overflow and washout. It is necessary to understand the hydrological properties of the landslide dam catchment area in order to predict the water level during flooding. However, in many cases, landslide dams that form in valleys in mountainous land do not have the structure of fixed beds in river channels. Here, we present a calculation of the hydrological balance of the landslide dam circumference for a rain event based on hydrological observations the runoff characteristics of the catchment area.

INVESTIGATION AREA AND METHOD

The investigation areas were two landslide dams, whose locations are shown in Fig. 1. The specifications of the two landslide dams are shown in Table 1, and a diagram of the

hydrological balance of the landslide dam is shown in Fig. 2. To understand the hydrological balance in terms of inflow, rate of flooding

increase/decrease, and other variables, the observations shown in Fig. 3 were performed. The hydrological balance of the landslide dam circumference was calculated by the following method.

Fig. 1 Scope of study area

Fig.2 The concept of the hydrological landslide dam circumference

(2)

・The depth–volume curve of the landslide dam was calculated using a laser scanner and acoustic doppler current profiler.

・The amount of change was calculated using the flooding water gauge.

・The groundwater level was measured in the boreholes of two or more landslide dams to determine the quantity of water that was leaking downstream from the flooding. This allowed calculation of the percolation area and hydraulic gradient by Darcy's rule using the inverse operation coefficients of permeability.

CONCLUSIONS

The hydrological balances of the rain event associated with typhoons no. 16 and 17 in 2012 in Nagatono and Kuridaira are shown in Fig. 4. In the Nagatono area, the rate of rain loss and water leakage amount was large compared with those in the Kuridaira area. There were few diversion channel flows at the time of typhoon no. 16 in the Kuridaira area. The opposite occurred at the time of typhoon no. 17, when the situation favored easy erosion in the Kuridaira area. By investigating the hydrological balance using this method, runoff

characteristics such as the amount of rainfall loss could be calculated to water level prediction during flooding.

Keywords: landslide dam, hydrological observation, hydrological analysis, hydrological balance

Tab.1 The summary of landslide dam

8.95 km2 5.1×106m3

100 m Kuridaira

4.63 km2 1.9×106m3

80 m Nagatono

Catchment area Reservoir

capacity The height

of the dam Area

8.95 km2 5.1×106m3

100 m Kuridaira

4.63 km2 1.9×106m3

80 m Nagatono

Catchment area Reservoir

capacity The height

of the dam Area

0 50 100 150 200 250 300 350

2012/9/16 6:00~2012/9/19 17:00 2012/9/30 10:00~2012/9/30 20:00 Event period (Kuridaira)

Height (mm)

Height of rainfall loss Height of leakage Height of change in flooding Height of diversion chanel dischage Height of drainage pump

0 20 40 60 80 100 120 140 160 180

2012/9/15 15:00~2012/9/19 12:00

2012/9/29 19:00~2012/9/30 20:00 Event period (Nagatono)

Height (mm)

Height of rainfall loss Height of reakage Height of change in flooding

no.16

no.17 no.17

no.16

Fig. 4 Hydrological balance of the two landslide dam circumferences on for typhoons 16 and 17 in 2012 Fig. 3 The hydrological balance observation method for

the landslide dam circumference Rainfall gauging Water-level

gauging

Discharge measurement (monthly)

Grandwater level

Water-level gauge Rain gauge

Using magnetic current meter Borehole

Rainfall

A laser scanner and acoustic Doppler current profiler surveys for depth-volume curve

Rainfall gauging Water-level gauging

Discharge measurement (monthly)

Grandwater level

Water-level gauge Rain gauge

Using magnetic current meter Borehole

Rainfall

A laser scanner and acoustic Doppler current profiler surveys for depth-volume curve

Referenzen

ÄHNLICHE DOKUMENTE

To decrease uncertainty of large-scale hydrological mod- elling results, new remote sensing information should be taken into account, including data on inland water lev- els,

snapshots of the saturation for the thin soil, high K, real slope configuration with semiarid forcing; (b) estimated by ParFlow-CLM; (c) following the TWI approach; and (d) the

The LSFLOW model is a simulation model that predicts the shape of the soil mass formed by a landslide, and we applied this model as a tool to predict the shape of a landslide dam

• They are proxyies for biomass development where biomass constitues the link between the water and carbon household via stomata (photosynthesis/transpiration). •

In the landslide longitudinal profile of Iya district, the calculated slid soil sediment zone and measured zone show relatively good resemblance, but in the

Using the inflow (=flow rate of leakage) into the landslide dam at the time of smaller fluctuation in the water level of the landslide dam, cross-sectional area of flow

When using LSFLOW to make a prediction, by setting the parameter φ s = φ m , it is possible to predict the shape of deposition with which the most dangerous dam height is

One of the results was a highly detailed, up-to-date map of land use, which was compiled from the digital cadastral map, aerial photography and the European Integrated